2001 Bond Referendum Summary |
|
|
Updates on construction projects funded by $51.8 million bond passed in 2001.
Bethesda Elementary School
- Design Consultant: DTW Architects and Planners, LTD
- Scope: An 8 classroom addition.
- Budget: Completed within budget.
- Schedule: Completed on schedule.
- $1,645,153
Oak Grove Elementary School
- Design Consultant: DTW Architects and Planners, LTD
- Scope: A 4 classroom addition
- Budget: Completed within budget.
- Schedule: Completed on schedule.
- $993,428
Pearsontown Elementary School
- Design Consultant: Coulter Jewell Thames, P.A.
- Scope: New driveway entrance, canopy and traffic patterns
- Budget: Completed within budget.
- Schedule: Completed ahead of schedule.
- $204,078
Watts Elementary School
- Design Consultant: The Roberts Group, P.A.
- Scope: A new stairwell replacing the old fire escape.
- Budget: Completed within budget.
- Schedule: Completed on schedule.
- $109,500
Durham School of the Arts
- Design Consultant: Coulter Jewell Thames, P.A.
- Scope: New driveway and additional parking.
- Budget: Completed within budget.
- Schedule: Completed ahead of schedule.
- $378,802
Mobile Classrooms
- Scope: Mobile classrooms to assist with flexible space during construction of bond projects.
- Budget: Completed within budget.
- Schedule: Completed ahead of schedule.
- $325,000
Facilities / Transportation
- Present Scope: Upgrade fuel distribution and management equipment.
- Budget: Budget adjusted upward for field conditions.
- Schedule: Completed on schedule.
- $236,402
Lakewood Elementary School
- Design Consultant: Boney Architects
- Scope: Extensive renovations in existing facility and a 28,000 s.f. addition that houses kindergarten, pre-k and EC classrooms, as well as a new administrative area and media center.
- Budget: Budget has been adjusted to accommodate unsuitable soils & rock outcroppings discovered during excavation and additional work was in parking lot.
- Schedule: Completed on schedule.
- $7,049,596
R.N. Harris Elementary School
- Design Consultant: The Roberts Group, P.A.
- Scope: A 27,500 s.f. addition that houses 4 kindergarten classrooms, 3 first grade classrooms, art room, music room, dance / drama room and new resource rooms. New parking area and playground courtyard included.
- Budget: Completed within budget.
- Schedule: Completed ahead of schedule.
- $3,680,808
Chewning Middle School Phase I
- Design Consultant: The Roberts Group, P.A.
- Scope: Extensive renovations to approximately 85,000 s.f. of existing space. (Balance of facility to be renovated as part of the 2003 bond program). Site work includes improvements to drive and parking facilities.
- Budget: Completed within budget.
- Schedule: Completed on schedule.
- $3,998,000
Carrington Middle School
- Design Consultant: DTW Architects and Planners, LTD
- Scope: Extensive renovations in existing facility and a 30,800 s.f. addition that houses 10 standard classrooms, vocational education space. Also included is anexpansion to the cafeteria and administrative areas and new stair towers.
- Budget: Budget adjusted for extended renovation and site needs.
- Schedule: Completed on schedule.
- Award: Durham City - County Appearance Commission’s Golden Leaf Award of Merit 2006
- $8,408,999
Rogers-Herr Middle School
- Design Consultant: Boney Architects
- Scope: New additions totaling 45,000 s.f. including a 2-story addition that provides 7th and 8th grade classroom space, science and foreign language space. A new guidance and career center is located on the second floor. Another addition provides new space for band, choral and art. Site improvements include a new bus loop, new parent drop off, extensive new parking, new football, baseball, and softball fields.
- Budget: Within budget.
- Schedule: Schedule adjusted for permitting. Athletic fields and detention pond being finalized.
- Award: Durham City - County Appearance Commission’s Golden Leaf Award of Merit 2006
- $11,909,283
Creekside Elementary School
- Design Consultant: The Freelon Group
- Present Scope: New 80,000 s.f. elementary school serving a capacity of 630 students.
- Budget: Completed within Budget.
- Schedule: Completed late; Opened January 2005
- $11,903,580
Neal Middle School
- Present Scope: Connect school to city water.
- Budget: Within Budget.
- Schedule: Project was rescheduled due to coordination with a local development project that can save significant bond funds.
- Projected Completion Date: Winter 2005
- $350,000
|
|
|
|